Rhoslyn Bridge

From Festipedia, hosted by the FR Heritage Group
Jump to: navigation, search

[edit] Lower section

Rhoslyn Bridge
Previous Station Tan y Bwlch
Previous Location Campbell's Platform
Status In Use
Next Station Dduallt
Latitude 52:57:33N
Longitude 3:58:09W
Grid Reference SH678420

Grid Reference :SH678420 Lat / Long :52.95909 / -3.96918


Deviation Locator
Deviation Sites.gif
Towards Porthmadog Campbell's Platform
Toward Blaenau Ffestiniog Dduallt

Deviation

Dduallt

Part completed bridge, April 1969, showing columns in position

During the planning and execution of the deviation, a site, No. 4 was created for organising the spoil, and subsequent erecting of the bridge. Click here for more pictures of that time.

Rhoslyn Bridge allows the line to cross over itself at Dduallt and gain sufficient height to by-pass Llyn Ystradau. It crosses the old line at a narrow cutting just south of Dduallt station. It was necessary to cut back the cutting walls to allow for the supporting columns of the bridge.

Completed, from other direction, 39 years on, 2008


[edit] Upper Section

Rhoslyn Bridge
Previous Station Dduallt
Status In Use
Next Station Tanygrisiau
Latitude 52:57:33N
Longitude 3:58:09W
Grid Reference SH678420

Grid Reference :SH678420 Lat / Long :52.95909 / -3.96918


Deviation Locator
Deviation Sites.gif
Towards Porthmadog Cei a'r Bont
Toward Blaenau Ffestiniog Barn Site

Deviation

Dduallt

The eight columns, with cross-beams between each pair to form the four piers, were cast in situ in early January 1969 by a team from Westminster School under the direction of John Grimshaw and Bunny Lewis with John Harrison as loco driver and winchman. Ready-mixed concrete was delivered to Tan-y-bwlch and railed up the the site in skips, to be poured into the shuttering.

Temporary spans were installed in autumn 1969, enabling material from Barn cutting to be carried over to complete Cei a'r Bont.

The temporary spans were removed in October 1970, and replaced by Dow-Mac prestressed concrete beams in January 1971. In March the deck was concreted using ready-mix delivered to Tan-y-bwlch and taken to site in Hudson wagons lined with polythene sheeting. Waterproofing of the deck and fitting of railings followed later.
Two locator blocks dependant on if you are underneath or on top!

[edit] See also

Personal tools
Namespaces

Variants
Actions
Navigation
Interaction
Toolbox